Project Introduction


Contract No.: SD/2019/03 Wan Chai Development Phase II - West Landscaped Deck and Other Roadworks

Contract Details

Scope: The works mainly include construction of the West Landscaped Deck at the west of Hong Kong Convention and Exhibition Centre and other associated roadworks.
Commencement Date: 8 July 2020
Completion Date: 2025 Third Quarter (Anticipated)
Contract Sum: HK$ 279 million
Contractor: Kin Chiu - China Railway First Group Joint Venture

Latest Progress

Piling and foundation works of the main deck had substantially completed. Pier and superstructure construction of the main deck are in progress. Road improvement works at Hung Hing Road , Wan Ying Street and Wan Shing Street completed.

Wan Chai Development Phase II (West Landscaped Deck and Other Roadworks)