Scope: | The works mainly include construction of the West Landscaped Deck at the west of Hong Kong Convention and Exhibition Centre and other associated roadworks. |
Commencement Date: | 8 July 2020 |
Completion Date: | 2025 Third Quarter (Anticipated) |
Contract Sum: | HK$ 279 million |
Contractor: | Kin Chiu - China Railway First Group Joint Venture |
Piling and foundation works of the main deck had substantially completed. Pier and superstructure construction of the main deck are in progress. Road improvement works at Hung Hing Road , Wan Ying Street and Wan Shing Street completed.